PECK CONSTRUCTION INC. -
Peck Construction and its customers are proud of the projects we have completed.  Here are a few examples of our work.
 
 
2009 CLEAN WATER PLANT EXPANSION
 
$2,095,056.00
 
Description:
A new wastewater treatment plant for the city of Justin, TX.
Two 60' diameter clarifier/aeration basins, chlorine contact chamber, two submersible lift stations, blowers, and headworks facility
 
Owner:
City of Justin, TX
 
Engineer:
Belcheff & Associates
Mike Anderson
(817) 491-2776
 
Completed:
December 2010
 
 
 
 
 
 
WASTEWATER SYSTEM IMPROVEMENTS
 
$1,336,511.00
 
Description:
A new 350,000 GPD package treatment plant for the town of Urania, LA
 
Owner:
Town of Urania, LA
 
Engineer:
Bryant Hammett & Associates
Keith Capdepon, Jr
(318) 757-6576
 
Completed:
December 2010
 
 
 
 
 
HARDY LIFT STATION IMPROVEMENTS
 
$1,343,058.00
 
Description:
Renovation of a sewer lift station in Shreveport, LA.
Three new 110 HP dry pit pumps, 16" header piping & valves, and odor control system
 
Owner:
City of Shreveport, LA
 
Engineer:
City of Shreveport Engineering Dept.
Barbara Featherston
(318) 673-6592
 
Completed:
June 2010
 
 
 
 
 
SURFACE WATER TREATMENT PLANT UPGRADE AND EXPANSION
 
$4,301,814.55
 
Description:
Expansion of the water treatment plant in Marshall, TX.
Two 100' diamter clarifiers, disinfection contact basin, wastewater recovery basin, two submersible lift stations, chemical building, and chemical feed facilities
 
Owner:
City of Marshall, TX
 
Engineer:
Stokes & Associates
Steve Wick
(903) 657-7558
 
Completed:
April 2009
 
 
 
 
 
LONG LAKE LIFT STATION IMPROVEMENTS
 
$309,427.00
 
Description:
Renovation of a self priming sewer lift station in Shreveport, LA.  New pumps & piping, wetwell lining, paving, and fencing.
 
Owner:
City of Shreveport, LA
 
Engineer:
City of Shreveport Engineering Dept.
Barbara Featherston
(318) 673-6592
 
Completed:
April 2009
 
 
 
 
 
ALLIGATOR BAYOU LIFT STATION IMPROVEMENTS
 
$330,622.00
 
Description:
Renovation of a sewer lift station in Bossier, LA.  New piping, wetwell lining, paving, and fencing.
 
Owner:
City of Bossier, LA
 
Engineer:
City of Bossier Engineering Dept.
Steve Vercher
(318) 741-8568
 
Completed:
February 2009
 
 
 
 
 
H & L POULTRY WASTEWATER TREATMENT PLANT
 
$1,625,846.00
 
Description:
A new treatment plant for wastewater from the
H & L Poultry processing plant in Warren, AR
 
Owner:
H & L Poultry
 
Engineer: 
McClelland Engineers
Stacy Akin
(501) 371-0272
 
Completed: 
August 2008